Meerwind Süd | Ost - Approval Process
| I | since 2001 | Ecological field studies |
| II | 2004 | Hearing with the Federal Office for Shipping and Hydrography |
| III | summer 2005 | Reappraisal of locations for Wind turbines according to the stipulations Water and Shipping Directorate (WSD) |
| IV | May 16, 2007 | Approval granted for OWP Meerwind Ost (40 turbines) and OWP Meerwind Süd (40 turbines) |
| V | February 1, 2010 | Court decision: Dismissal of Charge against Administrative Court Hamburg from October 26, 2009 |
| VI | November 2, 2010 | Unconditioned Grid Connection Certificate |