Meerwind Süd | Ost - Approval Process

I since 2001 Ecological field studies
II 2004 Hearing with the Federal Office for Shipping and Hydrography
III summer 2005 Reappraisal of locations for Wind turbines according to the stipulations Water and Shipping Directorate (WSD)
IV May 16, 2007 Approval granted for OWP Meerwind Ost (40 turbines) and OWP Meerwind Süd (40 turbines)
V February 1, 2010 Court decision: Dismissal of Charge against Administrative Court Hamburg from October 26, 2009
VI November 2, 2010 Unconditioned Grid Connection Certificate

 

In order to make our website secure, transparent and optimal for you, we are using cookies, but only those that are technically mandatory. Without these necessary cookies, our website cannot be used properly. Cookies are explicitly not used for marketing or analysis purposes or the like. Detailed information can be found in our privacy policy declaration. For further use of this website, you have taken note of the use of these technically necessary cookies.